Thursday, October 11, 2012

EDUC 6145 Week 6 Blog: Analyzing Scope Creep


Scope Creep of a Training Project


There are many situations in which a project, whether personal or professional does not go as planned. Unexpected changes such as additional activities being added in the middle of the project, someone on the project team leaving the department, or the stakeholders decide they want to move the project in a different direction. Even though changes are likely to happen in a project, there are ways that the individual who is managing the project can help control the scope of the project in order to get it back on track. In this week’s blog posting, I will be discussing a professional project that experienced issues related to scope creep.

So, what is scope creep?
According to Reference.com (2012), scope creep is when there are uncontrolled changes in the scope of a project. This can happen when a project is not properly defined, managed, or controlled. (Dictionary.com, LLC., 2012). Ultimately, this can cause much frustration among the project team and the project manager.

Project Background: A specific process that was being processed by staff in certain department was going to be handed-off and managed by staff in a different department within the organization. The new department did not know how to complete the steps in the process, so the employees needed to be trained on the new process. Some of the steps in the process were changing with the hand-off to the new department. Initially, eight weeks were provided to design, develop, and deliver the training for the staff once the content was handed off to the instructional designer.

Scope Creep Issues: First, once the designer began to develop the training, she discovered that the process steps were more complex than what was originally presented in the project kickoff, planning, and hand-off meetings. The instructional designer realized that more information needed to be obtained in order to create proper training for the staff and would require additional time to complete. As she looked at the project plan dates and her calendar, she knew there would not be enough time to develop a high quality training session for the staff. Secondly, assumptions were made by the stakeholders that the additional information would not hinder project being completed as scheduled. However, once the stakeholders began reviewing the training material a couple of weeks later, they realized the content in the material needed to be presented in a certain way in order for the process steps to make sense to the staff being trained on the process. Ultimately, what was supposed to be an eight week project, turned into a six month project!

What could have been done differently? If I had been in the position of managing the project, there are several methods I would employ to help manage these issues more effectively and control the scope of the project. First, I would have utilized the Change of Scope Document as Dr. Stolovich discusses in the first video this week titled “Monitoring Projects.” I would require the stakeholders to agree to the changes outlined in the document and provide approval. According Portney et al (2008), a change control system should be implemented in all project plans and should require approval in writing (Portney et al, 2008). In addition, I would ensure to analyze the overall impact of the change. According to Greer (2010, p. 36), the exact scope of the change should be clearly analyzed, including the “schedule, quality of the finished product, costs, project team assignments, including level of effort, and other deliverables, including their amount and quality” (Greer, p. 36, 2010). By clearly analyzing the complete scope of the changes, this allows the project manager to determine how the project will be impacted at all levels.

References
Dictionary.com, LLC. (2012). Scope creep. Retrieved October 11, 2012 http://www.reference.com/browse/Scope_creep
Greer, M. (2010). The project management minimalist: Just enough PM to rock your projects! (Laureate custom ed.). Baltimore: Laureate Education, Inc.
Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E. (2008). Project management: Planning, scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons, Inc. 


Word of the Day

This Day in History

Jackson Pollock Art

Juliet, the virtual kitty!